Government's Programme
of Action 2007 |
|
|
Economic Cluster |
||
|
Actions |
Departments |
Timeframe |
Progress update - 22 Jan 2008 |
||
|
1 |
ENSURING ALIGNED
AND SUPPORTIVE MACRO-ECONOMIC APPROACHES |
|
|
|
|
|
1.1 |
Establish
modeling and scenario planning programme for AsgiSA / NIPF goals |
NT, Presidency, DPE |
Nov-07 |
Completed
but continuing in POA 2008 |
|
|
1.2 |
Do review
of |
Presidency, |
Jul-07 |
Project
Completed. Studies completed and results presented at the Jul-07 Cabinet
Lekgotla |
|
|
1.3 |
Implement
pilot RIA system and introduce the regulation making procedures |
Presidency, NT |
Dec-07 |
Departments
are being approached to volunteer to be part of the piloting of RIA. Training
programmes and RIA website are being developed to ensure communication and
successful implementation of RIA |
|
|
2 |
BUILDING A
COMPETITIVE AND LABOUR-ABSORBING ECONOMY THROUGH INDUSTRIAL POLICY |
|
|
|
|
|
2.1 |
Begin
implementation of Export Strategy within context of National Industrial
Policy Framework |
DTI, DFA, Presidency |
Apr-07 |
Implementation
of the export strategy has begun and this activity is complete |
|
|
2.2 |
Increase
usage of ICTs by addressing pricing and other access-related issues |
DoC, DPE, |
May-07 |
ICT
policy directives announced. Process to harmonise legislation with the
protocol on the policy and regulatory framework for the NEPAD ICT Broad band
infrastructure network underway. Infraco Act promulgated |
|
|
2.3 |
Implement
R&D measures |
|
|
|
|
|
2.3.1 |
Implement
R&D tax incentives and other measures to raise R&D spending to 1% of
GDP. |
DST, |
Mar-08 |
Initiatives
to increase R&D to 1% of GDP have been implemented. The Ten-Year
Innovation Plan was approved by Cabinet hence new POA items will be
identified. processes for aligning the Ten-Year Innovation Plan and future
versions of the IPAP are underway |
|
|
2.3.2 |
Develop
mechanisms to support cutting-edge industries |
DST, |
Mar-08 |
Operational
plans for TIA by Apr-08 are underway and DST is considering including inputs
into the Bill certified in Oct-07. Processes to guide development of action
plans for research centre of competences for information security and
titanium finalised |
|
|
2.4 |
Implement
Cabinet decision on IPP including review of competition policy |
DTI, |
Dec-07 |
Completed
but continuing. The review of the competition policy has been completed and
will be presented to Cabinet in Jan-08. IPP negotiations with Mittal have
been reopened. Tariff review in major input industries is being initiated |
|
|
2.5 |
Implement
agreed-on sector KAPs (Key Action Plans) |
|
|
|
|
|
2.5.1 |
BPO |
DTI, DoC, Presidency |
Ongoing |
Implementation
of GAS programme has begun. Funding for the piloting of monyetla secured. Proposals
on developmental pricing of telecommunication are being finalised.
Implementation of the marketing strategy on track |
|
|
2.5.2 |
Tourism |
DEAT, DTI |
Ongoing |
2nd
economy implementation framework developed. 993 SMMEs have been supported
through the Tourism Enterprise Programme. Provinces continue to develop and
implement safety strategies. Visa applications Forum established. Airlift
Strategy has begun |
|
|
2.5.3 |
Chemicals |
DTI, Presidency |
Ongoing |
A review
of import duties on chemical inputs is underway. On increasing polypropylene
value-added products used in autos and packaging industries, a study is underway
to develop a business case |
|
|
2.6 |
Finalise
KAPs (Key Action Plans) |
|
|
|
|
|
2.6.1 |
Biofuels |
DME, Presidency |
Jul-07 |
Further
work to be done before the strategy is presented to Cabinet |
|
|
2.6.2 |
Forestry |
DWAF, Presidency |
Jul-07 |
Detailed
mapping of aforestation potential at 1:50 000 quaternary catchment scale have
been done and the maps will be used as a planning tool to assist in fast
tracking water licensing. Engagement initiated with DEAT on EIAs |
|
|
2.6.3 |
Clothing
and textiles |
DTI, |
Jul-07 |
KAPs have
been finalised and included in the IPAP. Implementation of recapturing the
domestic market, technology and industrial upgrading KAPs have begun. Country
of origin labeling regulations have been promulgated |
|
|
2.6.4 |
Metals
and engineering |
DTI, |
Jul-07 |
The
business plan sand funding for National Foundry Technology Network have been
finalised. Implementation of the national Tooling Initiative already underway
as a means to reduce manufacturing life cycle costs |
|
|
2.7 |
Develop a
framework for overarching strategies for the following sectors as basis for
prioritising interventions: mining/beneficiation, agriculture/agro
processing, white goods sector, retail, creative industries, community &
social services, pharmaceuticals, capital goods |
DTI, DAC, DME, DoE, DOH, DPE, DST, NDA, Presidency |
Jul-07 |
Draft
cluster perspective document completed |
|
|
3 |
MASSIVELY
INCREASE PUBLIC INVESTMENT |
|
|
|
|
|
3.1 |
Execute
and monitor system for infrastructure implementation and impact in particular
energy, water, ICT, ports, rail, air-transport, road as reflected in AsgiSA |
DPE, DME, DoC, DOT, DPLG, |
Aug-07 |
Project
completed. Monitoring systems established by National Treasury. SOE reports
will be submitted to NT for monitoring as per Cabinet decision |
|
|
3.2 |
Ensure
the public investment programme leads to greatest possible benefits for the
economy as cost-effectively as possible |
DPE, DEAT, DPW, |
Jun-07 |
Competitive
Supplier Development Plans are being developed by State Owned Enterprises.
Eskom, Transnet & PBMR are due in Mar-08 and PBMR by Jul-08 |
|
|
3.3 |
Implement
plans regarding multiple operators in rail and ports, and relationship
between operators and infrastructure in rail sector |
|
|
|
|
|
3.3.1 |
Finalise
Ports Investment Plan |
DOT, DPE |
Oct-07 |
Ports and
Rail master Plans completed and will be presented to the Cluster in 2008 |
|
|
3.3.2 |
Finalise
Rail Investment Plan |
DOT, DPE |
Oct-07 |
see 3.3.1 |
|
|
3.3.3 |
Merge
Shosholoza with Metrorail |
DOT, DPE |
Mar-08 |
Revised
proposal received from Transnet in support of MTEF process to be discussed
with Transnet. Business plan is to be reviewed in terms of Transnet's latest
proposal in Jan-08 |
|
|
3.3.4 |
Policy
decision on the relationship between operations and infrastructure |
DOT, DPE |
Oct-07 |
Draft
regulatory framework has been developed and is to be consulted with relevant
departments |
|
|
3.4 |
Provide
framework for regulators in each network industry (energy, telecoms, rail
ports), with clear responsibilities, clarity on concurrent jurisdictions, and
unambiguous policy objectives linked to Asgi-SA. |
Presidency, DEAT, DME, DoC, DOT, |
Dec-07 |
Following
roundtable discussions with departments and regulators in Jul-07, further
work was initiated to develop framework. International benchmark study to be
finalised by end Jan-08 and assessment of performance of SA regulators to be
finalised Apr-08 |
|
|
3.5 |
Provide
for robust, affordable and reliable ICT infrastructure |
All Clusters, |
|
|
|
|
3.5.1 |
Increase
access to ICT infrastructure by rolling out Sentech Wireless Broadband and
Infraco and implementing Digital Migration Strategy |
DoC, DLA, DPE, DPLG, DPW, DST, NT |
Dec-07 |
Capitalisation
of Sentech to provide wireless broadband for government services has been
finalised. ECA amendment has been gazetted to facilitate the licensing of
Infraco |
|
|
3.6 |
Begin
implementation of the public transport action plan |
|
|
|
|
|
3.6.1 |
Accelerate
implementation of taxi recap programme |
DOT, DPLG, DTI |
Dec-07 |
Implementation
of the Taxi Recapitaisation Programme is progressing well with over 12500 old
taxi vehicles scrapped and R674m paid out as scrapping allowance. The draft
law enforcement strategy is currently being processed for adoption |
|
|
3.6.2 |
Accelerate
implementation of reformed bus subsidy system |
DOT, DPLG, DTI |
Mar-08 |
National
Road Passenger Plan that provides for transformed subsidy system for buses
and recapitalised taxi vehicles has been completed. Implementation of the
reformed bus system will require additional funds |
|
|
3.6.3 |
Finalise
investment plan for public transport |
DOT, DPLG, DTI |
Aug-07 |
Terms of
reference of the passenger Rail Investment Plan approved and tender to be
awarded. Detailed operational plans are being developed in 2010 host cities |
|
|
4 |
EQUITY AND
DEVELOPMENT |
|
|
|
|
|
4.1 |
Develop
framework for massifying second-economy interventions including EPWP |
Presidency, DLA, DOT, DPLG, DPW, |
Jul-07 |
The framework
for the second economy developed and is being incorporated into the
Government's Anti-poverty strategy. Proposals are being developed to increase
the impact of current interventions |
|
|
4.2 |
Strengthen
micro-enterprises' ability to transact/ negotiate with larger firms through
supporting the creation of marketing cooperatives and trading associations |
DTI, DPLG, NDA, Presidency |
Aug-07 |
Ten
products for government procurement from small enterprises approved by
Cabinet, developing implementation protocols. Government to support small
enterprises to assist uptake |
|
|
4.3 |
Improve
access to finance for micro-enterprises |
DTI, DOA, NT |
Ongoing |
With
regard to leveraging R5 billion on the Financial Services Charter, Khula has
secured commitment from top four commercial banks to sign a revised credit
indemnity scheme |
|
|
4.4 |
Co-ordinate
interventions to reduce SMME regulatory burdens, including municipal by-laws
(integrated small and micro-enterprises) |
Presidency, DoL, DPLG, |
Jul-07 |
On
municipal regulations, a manual was developed to assist municipalities to
reduce the burden of red tape on small businesses. Discussions between social
partners was initiated looking at labour market issues and its impact on
small businesses |
|
|
4.5 |
Strengthen
integrated state financial and business development support for small
enterprises through strengthened institutional mechanism and more effective
co-ordination |
DTI, |
Jul-07 |
A
delivery network integrating both financial and non-financial support for
SMEs has been created throughout the country |
|
|
4.6 |
Improve
communication on Second Economy initiatives |
GCIS, DPE, DTI, Presidency |
Ongoing |
English
publication on Economic opportunities completed and translations into all
South African languages to commence. The 16 part radio series on the 12 SABC
language stations started. To finalise the scheduling on the Television
Series in Feb-08 |
|
|
4.7 |
Implementation
of Communal Land Rights Bill to improve the possibilities for better economic
utilization of communal land |
DLA, DOA |
Apr-07 |
Implementation
of CLaRA continuing |
|
|
5 |
ENSURE PRIORITY
SKILLS FOR THE ECONOMY |
|
|
|
|
|
5.1 |
Co-ordinate
the acceleration of skills development for design, engineering, artisans,
which are critical for advanced manufacturing, construction and cultural
industries |
|
|
|
|
|
5.1.1 |
Increase
the number of available artisans by resolving the issue of training routes |
DoL, |
Dec-07 |
Priority
artisan trades agreed for 2007 with an update for 2008 in progress. A
detailed database of artisans on contract for completion for 2007/08 is being
compiled. Service level agreements in progress |
|
|
5.1.2 |
Increase
output of engineers by developing capacity of relevant faculties in
universities |
DoE, |
Dec-07 |
The DOE to
finalise student enrolment planning exercise for 2007 to 2010 |
|
|
5.1.3 |
Identify
and resolve system challenges which affect performance of initiatives,
including SETAs |
DoL, |
Dec-07 |
All
scarce and critical skill data from SETA annual research processes is now
fully coded within a coding system known as Organising Framework for
Occupations |
|
|
5.2 |
Review
targets and strengthen integration and coordination of National Human
Resource Development Strategy (including NSDS and JIPSA) to ensure long-term
provision of core and critical skills especially in priority sectors |
DoE, DoL, DTI, Presidency |
May-07 |
A NHRDS
concept document has been developed and consulted with the NHRD Task team,
Skills Focus Group (SFG), Economic Cluster and the Presidency. ToR for the
three studies were developed and endorsed. The first study has been completed
and discussed |
|
|
|
|
|
|
|
Report Created: 22 Jan 2008 |